Loesche receives two LM 53.3+3 CS mills order | World Cement
The lead time for the main components of the mill is 9 months and the gearboxes are supplied within 12 months. The commissioning of both vertical roller mills is planned for the end of next year. The order follows a previous delivery, in 2012, of the LM 46.2+2 CS Loesche mill, which is still in operation.